Underground Jumbo Development

Meters of advance per shift, per day and per month from the round you drill and the jumbo that drills it, plus what a meter of heading costs you.
Underground development headings only: a twin-boom drill jumbo advancing a drift, crosscut, ramp or decline by drill and blast. It is not a bench drilling tool, not a continuous miner or roadheader model, not a ground-support design, and not a ventilation design. It sizes the jumbo's share of the cycle only: mucking, charging, blasting, re-entry and the rest of the ground support happen on other machines and are not in these numbers.

A twin-boom drill jumbo at the face of an underground development heading

Step 1: The heading

Everything downstream is per meter of this profile.

Step 2: The round

Hole depth and pull set your advance. Nothing else in this tool moves it.

Step 3: The jumbo cycle

Setup, drilling and support. What one face costs the machine in hours.

Step 4: The shift

The gap between the cycle and the shift is where development schedules die.

Delays, as recorded on shift reports. These are the eight the source measured.

Step 5: Your costs

These are yours, not the handbook's. The source is explicit that development cost is too site-specific to publish as a rate.

Step 6: Benchmark it

A published all-in band to sanity-check what you just built up.

Why your number should be lower. The band above is all-in: it pays for the mucking, the hauling, the shotcrete and the services as well as the hole. Everything on this page is the jumbo's share of the cycle, so landing under the band is expected. Landing over it means either your rates are high or the heading is much bigger than the one the band was measured on.
-
meters per shift
-
meters per month, one jumbo, all its faces
-
cost per meter
StepValueWhere it comes from

The round, drawn

Where the shift goes

Rock density, if you do not know yours
RockBank density, t/m³lb/yd³
Asbestos ore1.903,200
Basalt2.955,000
Bauxite1.903,200
Chalk1.853,100
Clay (dry)1.402,400
Clay (light)1.652,800
Clay (heavy)2.103,600
Clay and gravel (dry)1.502,500
Clay and gravel (wet)1.803,000
Coal (anthracite)1.602,700
Coal (bituminous)1.252,100
Coal (lignite)1.001,700
Copper ore (low-grade)2.554,300
Copper ore (high-grade)3.205,400
Earth (dry)1.652,800
Earth (wet)2.003,400
Granite2.414,000
Gravel (dry)1.803,000
Gravel (wet)2.103,600
Gypsum2.804,700
Limonite3.205,400
Iron ore (40% Fe)2.654,500
Iron ore (+40% Fe)2.955,000
Iron ore (+60% Fe)3.856,500
Iron ore (taconite)4.758,000
Limestone (hard)2.604,400
Limestone (soft)2.203,700
Manganese ore3.105,200
Phosphate rock2.003,400
Sand (dry)1.702,900
Sand (wet)2.003,400
Sand and gravel (dry)1.953,300
Sand and gravel (wet)2.253,800
Sandstone (porous)2.504,200
Sandstone (cemented)2.654,500
Shales2.354,000
Taconite3.686,210

SME Mining Engineering Handbook, Table 10.4-1, p. 933, after Atkinson 1992. Bank density is the rock as it sits in the ground, before it is blasted and swells, which is the same thing Table 12.2-1 calls rock density (wet) and the right number for this page. Pick the closest rock in Step 1 and it fills itself in. This table publishes every density twice, in tons per cubic meter and pounds per cubic yard, and the two agree across all 37 rows to within 1.7%, the gap being the book rounding the pounds column to the nearest hundred. The printed page also carries swell, fillability and digability columns; they describe loading the broken rock rather than drilling it, so they are deliberately not reproduced here.

What a jumbo drills, and how fast
Drilling methodDiameter, mmTypical depth, m Rate, m/minRate, m/hAccuracy, cm/m
Top hammer pneumatic jackleg25-50under 41.00602-5
Jumbo37-1004-101.67-3.33100-2001-3
Top hammer hydraulic jumbo37-1254-200.50-2.0030-1202-3

SME Mining Engineering Handbook, Table 7.2-1, p. 439. The meters per minute column is converted from the printed meters per hour, because m/min is the unit Table 12.2-2 states penetration rate in. The printed footnote is what makes these numbers mean the same thing as the field in Step 3: "drilling rates are for actual drilling and do not include time for drill retraction, boom relocation, collaring, etc. Drilling rates decrease as rock mass strength increases and may increase or decrease depending on the number and orientation of joints/blocks." This page counts boom relocation and collaring separately, as boom setup per hole, so do not fold them into the rate as well or you pay for them twice. The surface crawler and down-the-hole rows on the printed page are for bench drilling and are left out. Note that the worked example drills a 3.05 m round, shorter than the 4 m these rows quote as typical.

The published example, table by table
Physical development parameterMeasurement
Width, m5
Height, m4.5
Area, m²22.5
Rock density (wet), t/m³2.8
Overbreak, %5
Metric tons per meter (including overbreak), t/m66.2
Drill factor, charged holes/m²2.2
Number of charged holes50
Number of 100-mm cut holes4
Hole depth, m3.05
Pull, %90
Advance per round, m2.75
Metric tons per round, t181.6
45-mm-diameter face holes, meters drilled, m151
100-mm-diameter cut holes, meters drilled, m12.2
Total face meters drilled, m163.18
Rock bolt length, m2.4
Friction bolt holes per round5
Resin bolt holes per round8
Rock bolt meters drilled per round, m31.2
Total small-diameter meters drilled per round, m182.2
Face meters drilled per meter advance, m59.4
Total meters drilled per meter advance, m70.8

SME Mining Engineering Handbook, Table 12.2-1, p. 1153. Loading this page reproduces every row of it. The printed overbreak is 5%, not the 5.6% our first transcription carried: 22.5 m² × 2.8 t/m³ × 1.05 gives the printed 66.2 t/m exactly, and 5.6% does not. Read off the printed page and corrected.

Jumbo cycle componentMeasurement
Tramming speed, k/h4
Average distance between faces, km1
Tramming time, min15
Setup and markup time, min25
Total setup time, min40
Setup time (=engine hours) per cut, h0.7
Drill meters per engine hour, m/h272
Instantaneous penetration rate, 45-mm holes, m/min1.4
Instantaneous penetration rate, 100-mm holes, m/min0.7
Meters drilled, 45-mm holes, m182.2
Meters drilled, 100-mm holes, m12.2
Drilling time, 45-mm holes, min130.1
Drilling time, 100-mm holes, min17.4
Total drilling time, min147.6
Total drilling time, h2.5
Holes drilled (all types)67
Boom setup time per hole drilled, s55
Total boom set-up time, min61
Total boom set-up time, h1
Total set-up and drill time (2 booms), h3.5
Average penetration rate per boom, m/min0.71
Jumbo drilling time, h1.74
Change centralizers, min10
Rattle backs, min15
Installation time per rock bolt, min1
Total rock bolt installation time, min5
Total ground-support time, min30
Total ground-support time, h0.5
Total jumbo time per face, h2.9

SME Mining Engineering Handbook, Table 12.2-2, p. 1154. Two rows here are printed values this tool does not reproduce and does not use: drill meters per engine hour, and average penetration rate per boom. Neither follows from the other cells on the page. The boom rate comes out at 0.93 m/min on every route through the table we could find, against a printed 0.71, so they are shown as published and left out of the chain rather than having a derivation invented for them.

Development performance componentMeasurement
Days per year365
Days worked per week5
Days worked per month21.7
Shifts per day3
Shift length, h8
Shift change, h0.8
No face available, h0.6
No power, h0.5
Meetings, h0.2
Face not scraped, h0.2
No ventilation, h0.2
Pump/water problems, h0.1
Maintenance/breakdown, h0.1
Total delays, h2.7
Balance of shift available, h5.3
Faces drilled out1.82
Face advance per shift, m5.01
Face meters drilled per shift, m298
Total meters drilled (including rock bolts) per shift354.7
Meters drilled per month, m19,356
Face advance per working day, m15
Face advance per month, m325.6

SME Mining Engineering Handbook, Table 12.2-3, p. 1154. Measured at a mine where every jumbo had at least five faces available to it, so it was never waiting on a muck cycle.

Published all-in development costs
Development itemDimensions$/m$/ft
Drifts and crosscuts3.7 m w × 4.0 m h, bolted2,790–3,100850–950
Stope crosscuts3.4 m w × 4.0 m h, bolted2,550–2,900780–880
Stope attack ramps3.0 m w × 3.0 m h, bolted1,950–2,050600–630
Decline (contracted)4.9 m w × 5.5 m h, bolted, 152 mm shotcrete6,9002,100
Ventilation drift4 m w × 4.6 m h, bolted, 76 mm shotcrete3,850–4,0501,175–1,230
Ventilation raise2.4 m diameter, raisebored and lined6,2501,900

SME Mining Engineering Handbook, Table 12.5-1, p. 1220, in 2009 US dollars at ±25%, for fairly fractured and weathered ground in central Nevada requiring regular bolting with split sets on 1.2 m centers. This table publishes every rate twice, in dollars per meter and dollars per foot, and the two agree to better than 1% on all six rows above, which is an independent check that a transcription cannot pass by accident. The seventh printed row, for pump stations and shops, is deliberately not carried here: it is quoted per unit of volume, and the book's own metric column converts it with the linear foot-to-meter factor instead of the cubic one, making it roughly eleven times too small.

What a heading actually achieves
SituationAdvanceSource
Twin-boom jumbo, single heading, including stockpile bays47.5 m/weektypically 45 to 50 m/week
Twin-boom jumbo, single heading, main face only40 m/weekthe rate that holds over a 2-year program
Cadia East, 6.0 × 5.5 m, long round, full ground support283 m/montha record month, including stockpile bays (Willcox 2008)
Civil tunneling works400 m/monthexceeded, but not mine development

All from the SME Mining Engineering Handbook, p. 1153. The single-heading numbers are the ones to hold this tool against. A model built on five available faces describes a jumbo that never waits; a decline being driven off one face is a different machine doing a different job.

What this tool does not know. It sizes the jumbo, and only the jumbo. It does not muck the round, haul it, charge it, blast it, clear the fumes, shotcrete the back or install the resin bolts, and it does not know whether your loading fleet can keep up with the tons it produces. It has no view on ground conditions: a fault zone slows every number on this page and nothing here will tell you that. It does not design the charge, so the explosive figure is your rate applied to the tonnage, not a powder factor. The face is taken as a plain rectangle, which is how the source models it, so a real arched profile has slightly less area than this assumes. Every published value has been checked against the printed page.

Spending more time on spreadsheets than on the job?

We build the reporting and admin automation for mining contractors, so the numbers keep themselves.

Book a 20 min call

Worked example

Worked with the values this page loads with, so the method can be checked against the cited source without entering anything. Change any input above and the calculator recomputes; the numbers below stay as a fixed reference case.

Face area22.5 m²width × height, Table 12.2-1 p. 1153
Tons per meter of heading66.2 t / marea × 2.80 t/m³ × 1.050 overbreak, the published example, Table 12.2-1 p. 1153
Charged face holes49.5area × drill factor, carried unrounded as the source does
Advance per round2.75 mhole depth × 90% pull, Table 12.2-1 p. 1153
Tons per round181.6 ttons per meter × advance
Face hole meters151.0 mcharged holes × hole depth
Cut hole meters12.2 m4 relief holes × hole depth
Rock bolt meters31.2 m13 bolt holes × bolt length
= small-diameter meters per round182.2 mface holes + bolt holes, Table 12.2-1 p. 1153
= total meters drilled per round194.4 mall holes, Table 12.2-1 p. 1153
Total meters drilled per meter of advance70.8the number that scales your consumables, Table 12.2-1 p. 1153
Tramming time15.0 mindistance ÷ speed, Table 12.2-2 p. 1154
+ setup and markup25.0 minyour input
= setup per face0.67 hTable 12.2-2 p. 1154
Drilling, small-diameter holes130.1 minsmall-diameter meters ÷ face rate
Drilling, cut holes17.4 mincut meters ÷ cut rate
Holes of all types66.5charged + cut + bolt holes, each one a boom setup
+ boom setup61.0 min66.5 holes × 55 s
= setup and drill time, all booms3.48 hTable 12.2-2 p. 1154
÷ 2 booms = jumbo drilling time1.74 hbooms work the face together, Table 12.2-2 p. 1154
Ground support by the jumbo0.50 hcentralizers + rattling + 5 bolts placed, Table 12.2-2 p. 1154
= jumbo time per face2.90 hsetup + drilling + support, Table 12.2-2 p. 1154
Shift length8.0 hrostered
− recorded delays2.7 hthe eight categories in Step 4, Table 12.2-3 p. 1154
= balance of shift available5.30 hTable 12.2-3 p. 1154
= faces drilled out per shift1.82balance ÷ jumbo time per face, Table 12.2-3 p. 1154
= face advance per shift5.01 mfaces × advance per round, Table 12.2-3 p. 1154
= face meters drilled per shift298 mfaces × face meters, Table 12.2-3 p. 1154
= meters drilled per month19385 m× 3 shifts × 21.7 days, Table 12.2-3 p. 1154
= advance per working day15.03 m× shifts per day, Table 12.2-3 p. 1154
= advance per month, this jumbo326.1 mtotal across every face it services, not one heading, Table 12.2-3 p. 1154
Jumbos to hit 800 m/month3target ÷ advance per month, rounded up, p. 1153
Jumbo and crew per meter$798.51 / m$500/h × 8.0 rostered h ÷ advance per shift
Drilling consumables per meter$849.73 / m70.8 meters drilled per meter advanced × your rate
Rock bolts per meter$213.11 / m13 bolts × $45 ÷ advance per round
Explosive per meter$231.53 / mtons per meter × your rate
= cost per meter, jumbo cycle only$2093 / mthe four rows above
Published all-in benchmark$2,790–3,100 / mDrifts and crosscuts, 3.7 m w × 4.0 m h, bolted, 2009 USD ±25%, Table 12.5-1 p. 1220

See all the calculators