Meters per shift, holes per shift and cost per meter from the rock you are drilling and the pattern you are drilling to. Pairs with Surface Bench Blast Pattern: that one gives you the pattern, this one tells you what it costs to drill it.
Surface bench drilling only: vertical production holes to a bench. The published rates are for surface units and do not describe underground development drilling.

A blasthole drill rig working a bench in an open pit at night

Step 1: The rock

Two choices set the penetration rate. Nothing else moves it as much.

Step 2: The hole and the pattern

Take these straight from Surface Bench Blast Pattern.

Step 3: The shift

The gap between penetration rate and meters per shift is where the money goes.

Step 4: Your costs

These are yours, not the handbook's. The source says so: they come from the project.

-
meters per shift
-
holes per shift
-
cost per meter
StepValueWhere it comes from

Where the shift goes

What a meter costs

Penetration rate by rock strength and fabric
Rock fabric condition
Stable, uniformly competent ground55.033.530.524.5
Competent rock, fractured collar zone (top 0.6 to 1.2 m)49.530.027.522.0
Closed joints, fractured collar zone (top 0.6 to 1.2 m)42.025.523.518.5
Open joints, fractured collar zone (top 0.9 to 2.4 m)33.520.518.515.0
Heavily jointed, poorly cemented (top 1.2 to 3 m)27.016.515.012.0

SME Mining Engineering Handbook, Table 7.2-2, p. 440, in meters per hour. Read down for strength and across for fabric: the two together span 55 m/h at best to 12 m/h at worst, a factor of more than four. Fabric matters about as much as strength does, which is not how most rate-of-penetration estimates are made.

Drilling methods and what they are for
MethodDiameter, mmTypical depth, m Typical rate, m/hAccuracySource
Top hammer pneumatic jackleg25-50under 4 m602-5Table 7.2-1 p. 439
Jumbo37-1004-10 m100-2001-3Table 7.2-1 p. 439
Surface crawler-mounted drill50-1505-30 m20-1501-3Table 7.2-1 p. 439
Top hammer hydraulic jumbo37-1254-20 m30-1202-3Table 7.2-1 p. 439
Down-the-hole75-15010-50 m20-803-5Table 7.2-1 p. 439
Rotary, small (MD6200 class)127-200to 47.5 m multi-passn/an/aCat handbook p. 3-4
Rotary, mid (MD6250 class)152-250to 53.6 m multi-passn/an/aCat handbook p. 3-4
Rotary, large (MD6310 class)203-311to 74.6 m multi-passn/an/aCat handbook p. 3-5
Rotary, largest (MD6380 class)251-381multi-passn/an/aCat handbook p. 3-5

Percussive methods from the SME Mining Engineering Handbook, Table 7.2-1, p. 439; its rate column is a range across all rock types, so it is a sanity check on the figure from the table above rather than a substitute for it. That table stops at 150 mm, which does not reach a normal production bench hole, so the rotary classes come from the Caterpillar Performance Handbook rotary drill specifications, pp. 3-4 and 3-5. Caterpillar publishes no penetration rate with them, so no rate check is applied to a rotary selection rather than one being invented.

Bit life is the number to go and measure. Everything else here is either published or something you already know. Bit life varies more between sites than any other input on this page, and it sets the consumable half of your cost per meter. The handbook is explicit that drill bit and steel consumption comes from the project, not from a table.

Spending more time on spreadsheets than on the job?

We build the reporting and admin automation for mining contractors, so the numbers keep themselves.

Book a 20 min call

Worked example

Worked with the values this page loads with, so the method can be checked against the cited source without entering anything. Change any input above and the calculator recomputes; the numbers below stay as a fixed reference case.

Penetration rate90.2 ft/hMedium hard rock, competent rock, Table 7.2-2 p. 440
Hole depth34.0 ftyour input, bench plus subdrill
Time on bottom per hole22.6 mindepth ÷ penetration rate
+ move and set up6.0 minyour input
= cycle per hole28.6 min
Shift length12.0 hrostered
× mechanical availability× 0.85your input
× utilization× 0.80your input
= hours actually drilling8.16 h
= holes per shift17.1working hours ÷ cycle per hole
= meters per shift581.7 ftholes × depth
Rig cost per shift$2640$220/h × 12.0 rostered hours
Bit cost per shift$524581.7 ft ÷ 5000.0 ft bit life × $4500
= cost per meter$5.44 / ftboth costs ÷ meters drilled
Rock broken per hole377 yd³burden × spacing × bench
Rock broken per hole683 t× bank density
= drilling cost per ton$0.271cost per hole ÷ tons per hole