Job Cost and Margin, Mining and Heavy Civil Contractors

What one job has really cost you so far, what it has made, what each meter, metric ton or cubic meter costs you against what you bill for it, and whether you are over or under budget for how far along it is. Surface or underground, drilling, development, earthworks or haulage. It runs on your numbers only. No handbook publishes what a contractor's job costs, so there is no industry average on this page.

A contractor's site office at night with a job cost ledger, drill shift reports and a calculator under a work lamp

Step 1 - The work and what you bill

The numbers already in the boxes are an example, not a standard: a drilling job 1,200 meters in, billed at $95 a meter. Replace every one with yours, from your shift reports and your contract.

Step 2 - What it has cost you

Only you know these, and they come off your own timesheets, equipment hours and invoices. If you have to guess, the answer is a guess too.

Step 3 - Against the budget

Optional. Leave the budget at 0 to skip it. The comparison is the budget for the whole job scaled to how far along it is, so a job half done is held to half its budget.

margin to date
of revenue
cost per unit of work
against budget
StepValueWhere it comes from

Cost per unit, by where it goes

Budget against actual, so far

What this does not count. It counts what you put in and nothing else. It does not know about money you are owed but have not billed, a claim still in dispute, retention the client is holding, or the interest on cash you are waiting for. It does not forecast the rest of the job. It does not split equipment into ownership and running costs; the equipment rate is yours and so is that split. And it cannot tell you whether your hours are right: a job cost is only as good as the shift reports and timesheets it was built from.

Want this number every week without building it?

We build the reporting and admin automation for mining contractors, so the shift report feeds the job cost, the client report and the invoice without anybody typing it again.

Book a 20 min call

Worked example

Worked with the values this page loads with, so the method can be checked by hand, line by line without entering anything. Change any input above and the calculator recomputes; the numbers below stay as a fixed reference case.

Work done: 1,200 m × $95.00 per m$114,000your quantity, your contract rate
+ other billed$0your input
= revenue to date$114,000work × rate + other billed
Labor: 480 h × $62.00$29,760your hours, your burdened rate
Equipment: 440 h × $110.00$48,400your hours, your equipment rate
Consumables and materials$11,500your input
Subcontract$0your input
Unbilled standby: 30 h × $150.00$4,500your hours, your standby cost
= direct cost$94,160labor + equipment + consumables + subcontract + standby
Overhead: 12.0% of direct cost$11,299your allocation
= job cost to date$105,459direct cost + overhead
= margin to date$8,541revenue − job cost, the headline number
Margin as a share of revenue7.5%margin ÷ revenue
Cost per m: job cost ÷ 1,200 m$87.88what a unit of work costs you
Billed per m: revenue ÷ 1,200 m$95.00what a unit of work earns you
Budget earned: $190,000 × 55.0%$104,500your budget, scaled to how far along
= cost against budget (job cost − budget earned)+$959over budget if positive, under if negative