What one job has really cost you so far, what it has made, what each meter, metric ton or cubic meter costs you against what you bill for it, and whether you are over or under budget for how far along it is. Surface or underground, drilling, development, earthworks or haulage. It runs on your numbers only. No handbook publishes what a contractor's job costs, so there is no industry average on this page.
The numbers already in the boxes are an example, not a standard: a drilling job 1,200 meters in, billed at $95 a meter. Replace every one with yours, from your shift reports and your contract.
Only you know these, and they come off your own timesheets, equipment hours and invoices. If you have to guess, the answer is a guess too.
Optional. Leave the budget at 0 to skip it. The comparison is the budget for the whole job scaled to how far along it is, so a job half done is held to half its budget.
| Step | Value | Where it comes from |
|---|
We build the reporting and admin automation for mining contractors, so the shift report feeds the job cost, the client report and the invoice without anybody typing it again.
Book a 20 min callWorked with the values this page loads with, so the method can be checked by hand, line by line without entering anything. Change any input above and the calculator recomputes; the numbers below stay as a fixed reference case.
| Work done: 1,200 m × $95.00 per m | $114,000 | your quantity, your contract rate |
| + other billed | $0 | your input |
| = revenue to date | $114,000 | work × rate + other billed |
| Labor: 480 h × $62.00 | $29,760 | your hours, your burdened rate |
| Equipment: 440 h × $110.00 | $48,400 | your hours, your equipment rate |
| Consumables and materials | $11,500 | your input |
| Subcontract | $0 | your input |
| Unbilled standby: 30 h × $150.00 | $4,500 | your hours, your standby cost |
| = direct cost | $94,160 | labor + equipment + consumables + subcontract + standby |
| Overhead: 12.0% of direct cost | $11,299 | your allocation |
| = job cost to date | $105,459 | direct cost + overhead |
| = margin to date | $8,541 | revenue − job cost, the headline number |
| Margin as a share of revenue | 7.5% | margin ÷ revenue |
| Cost per m: job cost ÷ 1,200 m | $87.88 | what a unit of work costs you |
| Billed per m: revenue ÷ 1,200 m | $95.00 | what a unit of work earns you |
| Budget earned: $190,000 × 55.0% | $104,500 | your budget, scaled to how far along |
| = cost against budget (job cost − budget earned) | +$959 | over budget if positive, under if negative |
Estimating aid only. The answer is only as good as the numbers you put in. It is not an accounting figure, not an audit and not a quote. Check it against your own books. Full terms and disclaimer.