Truck Cycle Time & Fleet Match

How long one haul cycle takes, how many trucks it takes to keep the loader busy, and what the fleet actually produces. Pick a truck class and a material and the specs, speeds and cycle times fill themselves in from published tables.

Haul trucks climbing a switchback ramp out of an open pit at dusk

Step 1: The truck

Choosing a class fills in payload and top speed. Override either if you have the spec sheet.

Step 2: The loader filling it

The loader sets how long a truck sits under the bucket, which sets the whole fleet size.

Step 3: The haul road

Distance and road condition set the travel legs, which are usually most of the cycle.

Step 4: The fleet

How many trucks you actually have, and how well the operation is run.

-
cycle time, minutes
-
trucks to match the loader
-
bank tons / hour
StepValueWhere it comes from

The haul circuit

Where the cycle time goes

Speed factors: turning top speed into average haul speed
Haul section lengthft Loaded, starting from stopUnit already in motion
0–107 m0–3500.25–0.500.50–2.00
107–229 m350–7500.35–0.600.60–0.75
229–457 m750–1,5000.50–0.650.70–0.80
457–762 m1,500–2,5000.60–0.750.75–0.80
762–1,067 m2,500–3,5000.65–0.750.80–0.85
over 1,067 mover 3,5000.70–0.850.80–0.90

SME Mining Reference Handbook, 2nd ed., Table 12.3, p. 296 (after Bishop 1968). The calculator uses the starting from stop column for the loaded leg, because a haul cycle begins stationary under the loader. The empty return uses the same table's footnote: 0.55 / 0.60 / 0.65 of top speed under 152 m (500 ft), and 0.75 / 0.80 / 0.85 beyond it, for unfavorable / average / favorable conditions. Note that a factor can exceed 1.00 on a very short section if the truck enters it already at speed.

Rolling resistance by road surface
Ground surfaceEquivalent extra % grade
Gravel, well compacted, dry, free of loose material2.0
Gravel, not firmly compacted but dry3.0
Gravel, loose10.0
Mud with firm base4.0
Mud with soft spongy base16.0
Sand, loose10.0
Snow, packed2.5
Dirt, smooth, hard, dry, well maintained, free of loose material2.0
Dirt, soft, unplowed, poorly maintained4.0
Dirt, soft plowed8.0
Dirt, deeply rutted16.0

SME Mining Reference Handbook, 2nd ed., Chapter 13 (Haul Roads), p. 327. Rolling resistance is added to the real grade to give total resistance, which is what you check against the truck's rimpull chart.

Off-highway rigid-frame truck classes
Payload, tPayload, stTires Empty, kgGVW, kgTop speed, km/h
363918.00R3335,46071,21474
444921.00R3337,88882,10080
535924.00R3549,312102,73968
626824.00R3550,103111,81068
9210227.00R4972,412164,65468
13314733.00R51116,482249,47656
18320237.00R57141,249324,31858
22624940.00R57159,755386,00761
29032053.00R63231,332521,63160
31835056.00R63252,651570,16564
36340056.00R63260,815623,68968

SME Mining Reference Handbook, 2nd ed., truck specifications by gross vehicle weight, p. 320. The printed table gives every weight twice, in kilograms and in pounds, so each kilogram figure here was checked against its own pound figure by conversion. That is how three wrong digits in the machine transcription of this table were caught and corrected.

Passes to load a rigid-frame truck: a cross-check
Truck, t (st)15 m³20 m³ 25 m³35 m³45 m³
136 (150)543n/an/a
181 (200)65-643n/a
217 (240)n/an/a653-4
290 (320)n/an/an/a64-5
360 (400)n/an/an/an/a6

SME Mining Engineering Handbook, p. 937. Use this to sanity-check the pass count the calculator works out. Three to six passes is the range these tables are built around; if you land outside it, the truck and the loader are not well matched.

What this does not know. Average speeds here come from published factors on the truck's top speed, not from your truck's rimpull curve. On a long, steep, badly maintained climb the real loaded speed can be well below the factored figure. The calculator shows you total resistance for both legs so you can check it against the manufacturer's rimpull chart, and if the two disagree, trust the chart and type the speed in yourself.

Spending more time on spreadsheets than on the job?

We build the reporting and admin automation for mining contractors, so the numbers keep themselves.

Book a 20 min call

Worked example

Worked with the values this page loads with, so the method can be checked against the cited source without entering anything. Change any input above and the calculator recomputes; the numbers below stay as a fixed reference case.

Passes to fill by payload weight4.16Eq. 12.24a, p. 303
Passes to fill by body volumenot checkedno body volume entered
= passes used (rounded)4 passeslimited by weight (no body volume given)
Load per truck25.4 bank m³Eq. 12.25, p. 303
Load per truck59.6 t× bank density 2.35 t/m³
Loader cycle per pass33.0 sM-H, medium-hard digging, 11.5 m³ bucket
Spot time0.45 minoverlaps loading (Eq. 12.26a)
Spot + load time (Tl)2.20 minEq. 12.26, p. 303-304
Loaded average speed52.7 km/htop speed × 0.775, Table 12.3 p. 296
Travel out, loaded1.70 minEq. 12.18: 1500 m ÷ (v × 16.7)
Dump time1.00 minrear dump, p. 304
Empty average speed36.5 km/htop speed × 0.800, Table 12.3 footnote 2, capped by downgrade speed limit
Travel back, empty2.46 minEq. 12.18
= theoretical cycle (Tch)7.37 minEq. 12.19, p. 298
+ extra wait and delay0.00 minnone entered
= corrected cycle (TCch)7.37 minEq. 12.20, p. 298
Trucks to match the loader3.35Eq. 12.27: Tch ÷ Tl, p. 304
Operating efficiency0.73job Good / management Good, p. 302
Rate if trucks are the limit1064 t/hEq. 12.21 with 3 trucks
Rate if the loader is the limit1187 t/hone load per Tl
= production1064 t/hthe lesser of the two: trucks bound
Total resistance, loaded leg10.0%8.0% grade + 2.0% rolling, p. 327
Total resistance, empty leg-6.0%check both against the rimpull chart

See all the calculators